| Under Construction Project |
| Water Project Of
Al-Dalieh Axis |
|
Water resource "
Alsin water " with a capacity of 9000
m2/d. Its population is estimated at
approximately thirty thousand people and
waters forty villages and farms the most
important of which : Bastweir ,
Bsendianeh, Basna, Bshraghi, Beit
El-Allouni, Tal Al-Hweiri, Al-Jbeilieh,
Jaiboul, Bahzit, Hammam Al-Karahileh,
Kharayeb Salem, Dweir Bsendianeh,
Areikib, Ein Kbay, Zweibeh, Al-Dalieh,
Talazik, Beit Ana, Ein Ghannam, Harf
El-Sari, Fuwersat Sharkieh, Fuwersat
Gharbieh, Al-Msheirfeh, Maarin, Betshah,
Salamiah, Mshatieh, Wadi El-Kaleh,
Kassiba, Batmoush, Bsmalekh, Bshili,
Bjarneh, Al-Mansoura, Al-Kreidieh, Abou
Rjaileh, Al-Tahoun, Daem Dweir Baabdeh,
Baabdeh, Srebioun.
The project comprises of nine pumping
stations, thirty three tanks of
different sizes, with pumping lines and
the major and minor networks in about
346 km three hundred forty six
kilometers of different diameters.
The works of major and minor lines are
completely finished, and also the civil
works of pumping stations, tanks, except
some coverage works and the general
locations. The installation of
electrical and mechanical equipment are
finished and which are under
probationary pumping currently , and
also the lines of electrical feed were
executed and power transfers are under
construction. Works are in process as
per assigned plan to achieve the project
and to put it in exploitation during
this year and to inaugurate it on
Evacuation Day for 2006.
|
| Water Project Of
Stamo –Al-Jobeh Axis |
|
Water resource "
Alsin water " and that to feed a
gathering of population numbered for
more than 32000 according to the census
of 2000 and the number of its villages
about 50 villages and farms of which:
Stamo, Al-Cheikh Rih, Koummin, Markho,
Telaro, Bseika Al-Gharbieh, Bsrama,
Al-Fakhoura, Al-Leidineh, Al-Hassanien,
Bostan Al=Berkeh, Termi, Bhwara,
Bsaitroun,, Nkourou, Al-Kheshkhacheh,
Al-Mouallaka- Al-Kalamoun, Kefrez, Beit
Souhein, Wata Deir Zeino, Khreibat
Al-Kallaa, Bkailoun, Kalaat Al-Mahalba,,
Farzala, Al-Ariza, Beit Zantout, Znew,
Massit, Al-Bour, Bassout, Jobet Berghal,
Kherbet Al-Sindianeh, Mleikh, Malloukh,
Ananib, Ein Al-Sabie, Al-Belat,
Al-Karir, As-Sarraj, Al-Mseis, Markieh.
In addition to a series of villages
annexed to the Region of Lattakia, which
are : Al-Snobar, Chamiet Al-Mahaliba,
Al-Sendianeh, Al-Metrkieh, Kuweika, and
Ghio, and the support of water for the
villages of Dabbash, Yarteh,
Al-Jbeirieh.
The Project comprises of seven pumping
stations and sixteen major tanks with
different capacities. The length of the
lines and main water networks reach to
about 320 km , with diameters from 60 to
400 mm. Commencement is undergone in the
works of the major and minor lines as
from 2003. After securing the font pipes
necessary for the project, and
contracted to secure the electrical and
mechanical equipment for the pumping
stations corresponding with the
completion of the networks works and all
these works were finished according to
the schedule planned for them , and
commenced with the early 2006 the
experimental pumping to invite
thereafter the civilians for regular
subscription for counters.
|
| New Sin Refinery
Station at Al-Sin |
|
This project has
been noticed in the establishment plan
for 2003 in care to secure the potable
water necessary in quality and quantity
for the population increase in the
governorate in the city and the suburb,
knowing that the basic study for the
Third and Fourth Draw Lines was
completed for the supply of the
governorate with Al-Sin water without
refinery station, considering that the
water resource is Al-Sin Source directly
and that the specifications of its water
can be pumped directly without refining.
But to guarantee the arrival of water in
purely and permanently and within the
most accurate healthy and standard
specifications, and in view of the
change of water turbidity of Al-Sin
Source according to the seasons of the
year and specifically at winter with the
abundant maximal flows of the source,
the establishment has taken care in the
study and commenced to execute the new
refinery station for the new both draw
line which were put in exploitation
since that date.
The station is aimed to pass the
abundance of 2000 liters/ per second of
water through strata of sand and
intracit coal with thickness of 60 cm
sand and 40 cm coal.
The total cost for erecting this station
has reached about 200 Million Syrian
Pounds including the Contract of
Construction Works, and the Sand and
Intracit Coal Import Contract and the
Contract for the Electrical & Mechanical
Equipment, and the contract of the
permanent inlet from the lake to the
station. All the works of the contracts
are finished and ready to be put in
exploitation except the works of
permanent inlet , and which is under
completion where the main draw lines are
installed with a diameter of 1200 mm,
and the execution of the subsidiary
connections and their accessories are
now in execution between the main lines
and inlets of filtration basins of the
station and which are expected to finish
them in the second quarter of 2006.
|
| The Fourth Draw Line
Project |
-
The project is a
completion of the Fourth Draw Line
from Jableh cross-section to Besnada
Tank in Latakia, where in the basic
of the study of the Third Draw
Project , the study of executing a
line with 1400 mm diameter to the
city of Latakia was carried out in
1992, and due to the obstacle in the
process of contracting in securing
the font pipes necessary for the
project in the said diameter and due
to the very high prices submitted by
the limited companies producing the
pipes of large diameters. Therefore
, the search for available
substitutes was made, and the
substitute the execution of two
lines with 1000 mm where the
execution of direct line of 1000 mm
was carried out from Karfis Tank to
Besnada Tank and another line with a
diameter of 1000 mm from Karfis Tank
to Jableh city cross-section and
this line was called the Fourth Draw
Line.
-
The purpose of
completing the line is to secure and
cover the deficiency expected in
consumption of the city of Latakia
in addition to securing the
necessary water for the new projects
which will be put in exploitation in
period to come.
-
The length of the
line is about 26000/m.t. of elastic
font which is imported and the pipes
of which were distributed on the
execution path line to commence in
digging and installing after the
ratification of mutual agreement
contract with the General Company of
Water Projects, and the order of
commencement was given on 8-01-2006
for a period of execution of 200 Two
Hundred days.
-
The Total Value
of the Project has reached about 500
Five Hundred Million Syrian Pounds
including the value of the Import
Contract of the Pipes and the value
of Digging and Installing Contract.
-
Recently the
execution of equilibrium tank is in
execution in Karfis with the
capacity of 3000 m3 to secure the
feeding for this line, and also the
preparation of the technical study
is also carried to secure new
supporting pumps for the project and
to secure the required redundancy of
water and sufficient to the current
and futuristic needs of the city and
the villages of the coastal line.
|
ELECTRICAL &
MECHANICAL STATIONS REPLACEMENT PROJECT
FOR AL SEFSAF AXIS |
|
The purpose of the
project is to replace the old equipment
for the three axis stations and secure
new developed equipment with greater
abundance and to increase the productive
capacity to cover the increasing need of
the axis villages beneficiary from the
project with a total cost of about 24
Million Syrian Pounds. The project
includes securing six sets of horizontal
pumping with abundance of each 200 m3
/per hour and lift of 140 m for Al-Sin
station and sic sets of horizontal
pumping with the abundance of each
200/m3 and lift of 140 m for the Kasmin
Station, and two horizontal pumping set
with 70 m3/h abundance per each and lift
100 m for Al-Kalouf Station with all
necessary and sufficient accessories and
electric panels. This will be put in
exploitation in 2006 |
|
|
|
|
|
|
|